Showing posts with label concrete. Show all posts
Showing posts with label concrete. Show all posts

Monday, June 10, 2013

Week 3 Begins

Walls are poured and ready for the steel to be placed. There are tons of dirt that need to be removed and moved from the walk-out area, but Jim will be chipping away at that over the next few weeks along with back filling.

Exciting stuff!












Tuesday, June 4, 2013

Pouring the Walls!

1st day of week 2:
Jim just sent me this photo from his phone -- excavation is complete, footers in place, forms up and right now they are pouring the walls. Yay!


Friday, May 31, 2013

Day 3: More Excavation

The digging is taking longer than the contractor thought, but progressing nicely. Some of the footers are poured, the forms unloaded, and more dirt removed, but more needs to be done before the walls can be poured.